Finnieston Bridge Lift
Posted On August 2, 2014
By developer
And has No Comment
The bridge was constructed offsite and delivered to site on a suitably sized HGV transporter. It was then lifted into place on 14/07/2014 using a GROVE GMK 6300L crane. The total weight of the bridge is 28.0 Tonne and the total dimensions are: 21m(L) x 2m(H) x 6.6m(W) with 1m access walkways on each side. The height of the lift was calculated at 4m above ground level.